The Importance of BIM Management for Project Success

Share This Post

Share on facebook
Share on linkedin

Project Scope

Creating a database of underground BIM objects

CLIENT

Local Government Agency

Project Duration

5 Months

Our Approach

As part of Singapore’s Underground Masterplan project led by the Urban Redevelopment Authority, AcePLP was tasked to create a BIM database of all underground building structure in Marina Bay and Jurong Lake District, including any underground connection to buildings and train stations.

The BIM modelling requirements covered all underground components such as basement, piles, pilecaps, footings, retaining walls, external columns, knock-out panels, diaphragm wall, underground connections. It also included the internal layout of buildings, featuring vertical circulation cores such as lifts and staircases, structural walls, internal columns, beams, and slab.

The BIM database is to be geo-referenced to SVY21 for XY coordinates and Singapore Height Datum for the Z coordinates. Non-geometric information such as pile numbers are to be shown in the model. At the end of the project, AcePLP is also required to ensure that the modelled BIM database can be exported to IFC 2×3 format, with all geometries, attributes and parameters intact after conversion.

Solution: Achieve Unified Modeling Standards using Project Templates

The main challenge was that the original drawing information dated back several decades and featured incomplete information, largely due to the way that the drawings were presented. In the 2-dimensional form, errors in drawing information were not immediately clear, so these errors often made their way into the final As-Built drawings too.

With advances in 3D modelling technology, many of the mistakes became glaringly obvious, and had to be resolved. Resolving these errors sometimes required getting in touch with the team that made them several decades ago, particularly for old drawings. Where the errors cannot be resolved, the AcePLP team documented them so that future users of the BIM database are aware of the limitations of the database.

Given the wide scope of BIM modelling, a stringent BIM quality check process was implemented to ensure that the BIM models delivered were held up to a similar standard. The AcePLP BIM Manager set-up the project templates systematically to ensure that the BIM database was coherent across the team of 10 BIM modellers, who inadvertently had different modelling styles.

Autodesk Revit was used to create the BIM models. All models were federated via a network of sub-models to ensure that the model file size was manageable. As a result of the AcePLP model management method, the BIM models produced were easy to use even though the project involved a huge network of BIM models across two districts in Singapore.

This was the case even when the BIM models were exported and used as IFC files. The key takeaway is that the BIM management of a project is absolutely crucial in ensuring the usability of the final BIM deliverables.

BIM Software Used

Revit

More To Explore

gatspcmlogo
Case Study

Creation of BIM Design Models for MRT Lines

AcePLP was tasked to create (i) the horizontal and vertical rail alignments, (ii) running rails (iii) sleepers with baseplate and fasteners, (iv) third rail components, (v) bufferstops and (vi) to create a combined model of the sleepers and running rails throughout the 3D alignment, including turnouts.